James Craig Walk – Restorex project
Case study · St James Quarter, Edinburgh

James Craig Walk

A programme-rescue masonry package completed in 2021, including eight rebuilt chimneys, 15 stone dormers and elevation repairs to a Category B-listed Georgian terrace.

Project overview

The challenge

The main contractor approached Restorex to bring the masonry programme back into line after several previous contractors had been unable to provide the resources required. The project was operating under significant contractual time pressure, so the recovery plan had to increase productive capacity without compromising the accuracy expected on a Category B-listed building within Edinburgh’s World Heritage Site.

Restorex delivery

Restorex mobilised and properly resourced the masonry package, working with LDN Architects to resolve the specialist details and recover the programme. The works included rebuilding eight substantial chimney stacks, forming their moulded cope and blocking-course details, completing 15 stone dormer surrounds, and carrying out masonry repairs across the elevations. The high-level stonework was coordinated carefully with adjacent slate and lead junctions.

Outcome

Restorex completed the masonry works in 2021 and helped the main contractor recover a programme under severe deadline pressure. The finished roofscape combines eight rebuilt chimneys and 15 dormers with carefully executed elevation repairs, retaining the architectural character of the historic 1775 terrace within the wider St James Quarter development.

Scope highlights

  • Eight rebuilt chimney stacks
  • 15 stone dormer surrounds
  • Masonry repairs to the elevations
  • Programme recovery and resourcing

Completed
2021

Location
St James Quarter, Edinburgh

Building environment
Category B-listed city-centre restoration

Technical coordination

LDN Architects detail drawings

The drawings record the stone dormer-surround junctions and the chimney cope sections developed during coordination between Restorex and LDN Architects. Select either drawing to view it at full size.

LDN Architects drawing L(SK)098 showing works to the stone dormer surrounds at James Craig Walk
Stone dormer surrounds — LDN Architects drawing L(SK)098, 21 February 2020.
LDN Architects drawing L(SK)099 comparing chimney cope stone sections including the Restorex front chimney proposal
Chimney cope stone sections, including the Restorex front-chimney proposal — LDN Architects drawing L(SK)099, 25 August 2020.